Project 1
Aim: To schedule the construction of a main school building (G+2) Procedure: Step 1: 1) Open the Enterprise tab 2) Select OBS 3) Click add and add the new obs as Project Manager Step 2: 1) Click Enterpriset tab 2) Choose EPS and click add 3) Rename the eps as Skill lync education 4) Assign OBS as Project manager…
23 Aug 2022 06:15 AM IST
Project 2
Q1) & Q3) Aim: Develop the schedule after creating the new project, Create and assign resources Procedure: Step 1: Creating the project 1)Go to the Enterprise menu and click on projects 2)Go to the file menu and click on new 3)Choose the EPS node under which you need to create the project.(Same as that of project 1) 4)…
03 Oct 2022 10:04 AM IST
Project 1 - Developing the Schedule for the “Construction of Police Station Building”
Project 1 Q1) What would the simplest work breakdown structure for this project? WBS ID WBS Name 1 Clearances 2 Design 3 Procurement 3.1 Civil 3.2 MEP Items 4 Construction 4.1 Sub structure 4.2 Super structure 4.3 Steel / Enveloping Works 4.4 Finishes works 4.5 External Works 5 Testing…
03 Nov 2022 04:28 PM IST
Project 1
1) 1A) To select the right corridor for Kochi Metro, different possible options were tried.The three main options tried were Alwaye to Vytilla Kalamassery to Thripunithura Alwaye to Thripunithura Based on the expected ridership of the corridor, Alwaye to Thripunithura was selected. For this corridor, two-extensions…
19 Dec 2022 06:33 AM IST
2 Course Certificates
Academic Qualification
B.Tech
Vimal Jyothi Institute of Management and Research
01 Mar 2011 - 10 Mar 2015
12th
Chinmaya Vidyalaya
01 Mar 2010 - 10 Mar 2011
10th
Presentation Higher Secondary School
01 Mar 2008 - 10 Mar 2009
Here are the courses that I have enrolled
Similar Profiles
Ladder of success cannot be climbed with hands in pocket.
The Future in Motion
The future in motion
Passionate to learn